On a chilly Saturday last January, Defense Secretary Dick Cheney
headed to the Pentagon to meet with a small band of senior officials,
including Navy Secretary H. Lawrence Garrett III. The capital
was in the throes of Persian Gulf war fever, but this January
5 session focused on another crisis: what to do about the Navy's
A-12 aircraft, which was at least $1 billion over budget, 8,000
pounds overweight, and eighteen months behind schedule.
Secretary Garrett argued for a federal bailout to rescue the
plane. Others demurred. After six hours of discussion, Secretary
Cheney dropped a bomb: He would reject a bailout. He would kill
the A-12 outright.
The Secretary's summary execution of the A-12 abruptly ended
the saga of a plane that, six months earlier, enjoyed broad congressional
support and appeared problem-free. The stealthy, carrier-based
attack plane had been naval aviation's top priority since 1984.
What caused it to nosedive from preeminence to oblivion?
Investigators and officials place the blame on four factors:
- Overly protective Navy officials, who didn't want to endanger
the plane by pointing out problems. A Pentagon analyst first
detected a possible cost overrun two years ago, but the Navy
program manager continued to describe the A-12 as being on track
until after a major Pentagon review last year.
- A "don't-rock-the-boat" segment of the Pentagon
bureaucracy, which was aware of the problems but apparently reluctant
to buck its superiors to press its case. In one incident, a report
noting A-12 problems was tucked away and forgotten.
- Overly optimistic A-12 contractors, who miscalculated the
extent of the technical difficulties in producing such a plane
and shielded the problems from the government. An inquiry by
Navy Deputy General Counsel Chester Paul Beach found that General
Dynamics and McDonnell Douglas discovered "increasing cost
and schedule variances" but did not alert the Navy in a
timely fashion.
- Excessive secrecy, which blanketed the project and prevented
examinations that might have brought problems to light. Officials
assigned to Secretaries Cheney and Garrett were kept away, standard
reporting procedures were abandoned, and information was transmitted
verbally rather than in writing.
Secretary Cheney's kill order, unveiled January 7, rocked the
defense community. It left the Navy struggling to find a successor
to its A-6 jets and worsened the woes of the aerospace industry.
The disaster forced the resignation of Under Secretary of Defense
for Acquisition John Betti and the sacking of two Navy admirals
and a captain. It effectively ended the Air Force's program to
develop a derivative of the A-12 to replace F-111 and F-15E aircraft.
Suspicion and Ambition
A-12 development began early in the 1980s. In January 1988,
the Pentagon awarded General Dynamics and McDonnell Douglas a
contract worth $4.8 billion for full-scale development, including
production of eight prototypes. It later added contracts of $1.2
billion for Lot 1 production of six aircraft and $200 million
in long-lead funds for Lot 2.
Plans called for production of 858 aircraft. First, the Marine
Corps opted out of the program, reducing the planned buy; then,
due to tight budgets, Secretary Cheney pared the buy to 620 in
April 1990, though he continued to endorse the program.
Until last June, the A-12 appeared to be in good shape. According
to the inquiry conducted by the Navy, however, the program fell
into trouble almost from the outset. At the heart of the crisis
were technological challenges inherent in creating such an advanced
aircraft.
The biggest problem, say officials, stemmed from the difficulties
of creating and applying highly advanced composite material in
the radar-evading stealth plane. The two contractors had inadequate
experience with this material to carry out the project smoothly
and with a minimum of delay.
Evident mutual suspicion between the two contractors compounded
the problem. One Pentagon analyst who studied the issue said the
two A-12 contractors appeared loath to share sensitive technology
to further the A-12 program. The reason: They were competitors
on another project--the program to build the Air Force's Advanced
Tactical Fighter. (That project pits a team of Lockheed, General
Dynamics, and Boeing against Northrop and McDonnell Douglas.)
"There were technologies that could have helped in the
overall [A-12] effort, but they weren't willing to share those,"
said the analyst. "If you have a technological advantage,
how willing are you to share that if . . . it could help you in
some other program?"
An overly ambitious schedule exacerbated the problem. Under
the original timetable, the contractors planned first flight for
June 17,1990. They mapped out a design-to-assembly schedule of
only nine months, far shorter than the fourteen months normally
allotted for such an effort.
Workers in top-secret areas of plants operated by General
Dynamics in Fort Worth, Tex., and by McDonnell Douglas in Saint
Louis, Mo., would spend four and a half months on subassembly.
Sections would be shipped to Tulsa, Okla., for final assembly.
According to the report, the manufacturers were only feeling
their way along. They lacked proper tooling, missed key target
dates at various steps in the development process, and were forced
to issue "stop work orders" because of engineering problems.
Delays in the arrival of parts further delayed production.
"Evidence of Trouble"
When the program manager's production oversight team assembled
in the summer of 1989 to begin working toward a first flight in
June 1990, the contractors should have had a firm design in hand
for their manufacturing elements. "Hard" (production-quality)
tooling should have been on the assembly floor by September 1989.
Instead, Navy counsel Beach said, "there was early evidence
of trouble affecting the production schedule. The amount of engineering
effort required by the design of the airframe . . . was the first
indicator that first flight of June 1990 would slip. By then,
the first flight date of June 1990 was likely unattainable due
to lack of ample tooling and parts flow."
Late release of engineering design drawings delayed other development
stages. "In addition to the tooling problems," said
Beach, "further delays in initial fabrication of the composite,
sheet metal, and machined parts pushed back the initial-load dates
for assembly jigs and fixtures."
Somewhere along the line, the contractors began to see that
they had made a gigantic mistake in taking on the program under
a fixed-price contract, which the Navy had imposed in an effort
to get a grip on weapons costs. It was too inflexible to allow
for unforeseen costs, say industry and Pentagon officials, even
though such costs are inevitable when contractors are working
on the frontiers of technology.
Moreover, the aerospace contractors, who had sustained financial
setbacks because of government defense cuts, were under pressure
from upper management to maximize cash flow. They relied heavily
on progress payments given at various points in the development
process, Beach said.
"Such pressure would create an incentive to be optimistic,"
since progress payments would be reduced if the contractor or
the government estimated an overrun, said the Navy lawyer.
Beach also said that the progress payments were poorly scrutinized
by the government. In one instance, the Navy signed off on three
contract line items, even though work on each was not yet complete.
Payments were also approved for work that was substantially below
requirements, Beach said.
Consequently, the contractors, with approval by the Navy, "fostered
the illusion that internal program milestones had been successfully
passed" when critical elements of the contract "had,
in fact, only been pushed downstream."
The technical and schedule problems set the stage for the eruption
of fatal political problems in 1990. Secretary Cheney had been
a strong supporter until early last summer, when he learned of
major difficulties leading to cost overruns and delays. These
had not been detected during a nineteen-week-long Major Aircraft
Review (MAR) of the A-12 and three other planes: the Air Force's
B-2, C-17 transport, and Advanced Tactical Fighter (ATF).
A Clean Bill of Health
Following the MAR--and as a direct result of it--Secretary
Cheney appeared before Congress and on several occasions gave
the A-12 a clean bill of health.
Later, Pentagon probes showed that the program at that time
had been floundering and no one had thought to let the Defense
Secretary in on the secret. This outraged the Defense chief when
he heard of it, and it set the stage for his January 5 kill order.
Investigations by Beach and by Defense Department Inspector
General Susan Crawford indicate that top officials in the Navy
and DoD were aware of the problems but, for various reasons, either
didn't react or didn't follow through.
They pointed out that Secretary Cheney himself was present
at briefings in March and Apri11990 in which briefers raised the
issue of a potential $1 billion overrun on the A-12 program. Under
Secretary Betti, Cheney's top procurement officer, gave short
shrift to the estimate, and the discussion veered off in a new
direction.
In another instance, a Pentagon staff member received a report
about potential delays. He later said that he simply put it aside
and forgot about it.
Until his forced transfer in December, the Navy's principal
overseer for the A-12 program was Capt. Lawrence G. Elberfeld,
an aviation engineer with three advanced degrees. As program manager
since June 30, 1986, Captain Elberfeld had full authority and
responsibility for the program. He commanded a small staff with
assistance from onsite personnel at the two defense plants.
As portrayed in Beach's investigation, Captain Elberfeld was
protective of the A-12 and showed "good news" slide
presentations to accentuate the positive, despite increasingly
ominous signs. However, Beach also backed Captain Elberfeld's
claim that he "repeatedly and forcefully" told superiors
of "major challenges in the program" and that "he
insisted at all times on candor."
One early indication of trouble came from a Navy cost analyst,
who in March and July 1989 presented Captain Elberfeld with a
range of cost estimates predicting that the contract could exceed
the ceiling by as much as $200 million.
In reports to superiors in November 1989 and February 1990,
Captain Elberfeld replaced the analyst's estimate with a lower
calculation, "which he believed would result in an improvement
in the contractor team's cumulative cost performance," according
to the Beach investigation.
The Pentagon's own comptroller, in an October 1989 budget recommendation,
warned that the A-12 program was two years behind and $500 million
over ceiling. The budget recommendation and its accompanying forecast
were shelved because "no one agreed with us," according
to an analyst in the comptroller's office.
One Day, One Billion Dollars
The news got worse. On March 26, 1990, Deputy Director for
Cost Management Gary Christle, an independent cost analyst assigned
to Under Secretary Betti's office, was brought in to review the
A-12 program. One day later, after gaining access to classified
A-12 data, Christle concluded that the program was $1 billion
over budget and a year behind schedule. Christle's own boss, Under
Secretary Betti, refused to take the warning seriously.
In spite of the warning signs, Captain Elberfeld continued
to present the A-12 as an unqualified success. In an April 14,
1990, briefing, he made no mention of the $1 billion cost overrun
estimate and said the A-12 was "on track." He also warned
that renegotiating the contract would strap the Navy with legal
liabilities. On April 26, not long after the conclusion of the
MAR, Secretary Cheney appeared on Capitol Hill to reassure key
Senators and congressmen that the program was doing well.
Then the roof began to fall in. On May 4, 1990, eight days
after Secretary Cheney's congressional appearance, Captain Elberfeld
evidently had a frank talk about the A-12 with the two contractors
and soon began to revise his optimistic assessment. "For
the first time, they acknowledged a very strong likelihood they
would exceed their ceiling costs," Captain Elberfeld told
investigators.
The program manager, now worried, called a briefing three days
later to alert his superiors. One of the officials, Rear Adm.
John F. Calvert, the A-12 Program Executive Officer, resisted
taking the problem further up the chain of command to the Navy's
Assistant Secretary for Research, Development, and Acquisition,
Gerald Cann.
"I'm not going to take a problem to [Cann] without a solution,
because if I do, he may give me a solution I may not like,"
Admiral Calvert reportedly told his subordinate. Captain Elberfeld
then recommended a candid briefing for Cann to air the problems
but was told by Admiral Calvert to reduce his points to a two-page
working paper.
The working paper was further edited to one page. At a subsequent
meeting between Captain Elberfeld and his Navy bosses, they decided
not to tell Cann about the problems disclosed by the contractors
on May 4. Admiral Calvert told Captain EIberfeld not to bring
his talking paper to a meeting with Cann to discuss the Lot 1
purchase of A-12s. During the meeting, Captain Elberfeld kept
quiet. To do otherwise, he said, would "have been contrary
to [Admiral Calvert's] desires."
Others in the Pentagon were sluggish in responding to the bad
news. Although Christie's $1 billion estimate was discussed in
two briefings with Secretary Cheney, Betti said he made no effort
to raise it as a "red flag" because he considered the
analyst a "new kid on the block" unfamiliar with the
A-12.
Problems weren't brought to Secretary Cheney's attention until
June 1, when the contractors officially advised the Navy of severe
delays and cost overruns and pushed the first flight to December
1991. The Pentagon then ordered inquiries to determine why the
problems had not surfaced during the recent MAR.
Visions of a Bailout
In a December 17 letter, the Navy's Assistant Commander for
Contracts, Rear Adm. W. R. Morris, informed the two contractors
that they had "failed to fabricate parts sufficient to permit
final assembly" and had failed to meet specification requirements.
He ordered the two aerospace giants to show cause why the Navy
should not cancel the contract for default.
Still, few expected Secretary Cheney to kill the A-12. Most
predicted that the January 5 "show cause" meeting would
result in a government bailout to keep the airplane going.
Pentagon spokesman Pete Williams described the discussions:
"[Secretary] Garrett did all the early talking, kind of laid
out for [Secretary Cheney] what he thought the issues were and
walked through his recommendations. Then Yockey [Donald Yockey,
then the acting deputy secretary for Acquisition] made a follow-up
presentation. They both kind of described the current problems
with the contract and where we should go from there."
After that meeting, Secretary Cheney met for about an hour
and a half with a smaller group that included Joint Chiefs of
Staff Chairman Gen. Colin Powell, Deputy Defense Secretary Donald
J. Atwood, and "only a few other people," Williams recalled.
The Pentagon spokesman said the choices boiled down to three
options: carrying out the existing contract despite its problems,
modifying the contract to bailout the manufacturers, or terminating
the program.
"The general view," Williams said, was that the current
arrangement was "not going to work" and that "the
contractor cannot proceed under the current contract." The
choice was between a bailout or a termination, and the issue focused
on money. "Every time [Secretary Cheney] asked about additional
costs, he was told that no one could be sure," Williams said.
"That was part of the problem."
Was that a dominant factor in Secretary Cheney's decision?
"Absolutely," said Williams.
The Pentagon chief made up his mind after the meetings and
called Secretary Garrett late Saturday afternoon. "I don't
want a bailout," Williams quoted Secretary Cheney as saying.
Now unable to continue the program, the Navy formally canceled
the contract on Monday, January 7. The contractors were first
informed by Admiral Morris. They were told that the contract was
terminated for default.
General Dynamics and McDonnell Douglas stated that they did
not agree that they were in default and that they would contest
Secretary Cheney's decision and his characterization of the condition
of the program.
How could such a fiasco occur? Williams said that Secretary
Cheney had always been led to believe the program was on track.
Even though the Secretary attended the two Pentagon briefings
during the spring in which an estimated $1 billion overrun was
mentioned, according to a Navy inquiry, Williams said that Cheney
didn't react strongly because he was still being led to believe
the problems were manageable. "The constant message to him
was: 'Don't worry, we've got this under control.' "
Was Secretary Cheney's credibility hurt as a result of the
A-12 imbroglio? "I think he's concerned that he went out
and told Congress one thing, and he found out later that another
thing was the case," Williams reports, "but I don't
think his long-term credibility suffers for it." .
David Montgomery is Washington bureau chief
of the Fort Worth, Tex., Star-Telegram. He has extensively covered
General Dynamics and the A-12 project. This is his first article
for AIR FORCE Magazine.